Thursday, April 29, 2010

Day 13

The weather remains cold. Ice has returned and is thick for several hundred yards out from the site.

Removal of the sections and pieces continued via the highline. The crew is getting the difficult pieces, the ones that fell away from land. It involves using the come alongs (turfers) and the highline to get the pieces into position for lifting to the staging site.

The crew continued to police the area for the many small pieces that are a result of the mess that was on board.

Very little remains standing, essentially only the mast with the guy wires.

No comments:

This website was prepared by the MCA Foundation under award number NA09NMF4630309 from the National Oceanic and Atmospheric Administration, U.S. Department of Commerce. The statements, findings, conclusions, and recommendations are those of the author(s) and do not necessarily reflect the views of the National Oceanic and Atmospheric Administration, or U.S. Department of Commerce.